Excerpted from the September 2012 issue of ProNetwork News, part one of a two-part series:
What if Caesar had written “I came to the project site, I observed for general conformance with the Contract Documents but not for means or methods or work covered since my last visit” and then wrote a three word report? Caesar was a master of understatement and understatement leads to misunderstandings and, well, understatement. Architects have always faced liability for undiscovered construction defects but current economic times have forced many contractors out of business. With the typical lack of contractor insurance for defective work, A/E’s are the only solvent or insured pocket, leaving design professionals more vulnerable to construction defect claims than in the past.
Veni – I went to the site
Those preaching risk reduction used to urge that architects and engineers leave construction administration to construction managers and contractors. This approach allowed or even encouraged contractors, CMs, program managers and owner’s representatives to take market share for services formerly performed by A/E’s. It also missed the point. Design professionals do not seek to eliminate liability, but to manage the reasonable risks of design practice. Reasonable risks are those placed with the party able to control them.
If an owner wants an A/E to ensure perfect construction, the project is doomed to fail for two reasons. First, there hasn’t been perfect construction since the Pyramids (and they had different labor and insurance agreements in those days). Second, the A/E does not control all of the variables that go into a construction project. There are elements of construction installed and concealed by the time the A/E arrives for a weekly or monthly meeting and site tour and even the most gifted A/E is powerless to see through walls. Continue reading “Veni, Vidi, Vici, Lis Pendens: I came, I saw, I got sued – Part 1 of 2”